Update on 434 Union St
July 18, 2019
At 434 Union St, Trim Phase I has been completed. All doors, closet shelving and baseboard are installed, Kitchen and vanities cabinets are scheduled to be delivered July 26th.
May 2, 2019
We’re officially on Phase II of Finishing at 434 Union Street!
Sheetrock taping finished mid-March and painting was started immediately thereafter.
March 19, 2019
Sheetrock is 100% complete at 434 Union Street!
January 4, 2019
Construction is in high gear at 434 Union Street! Phase-2 of framing is officially finished. Insulation and sheetrock are now underway.