Update on 494 7th St
July 10, 2019
At 494 7th St. sistering and reinforcing of the existing joists along with bulkhead and roof framing are ongoing and estimated to be completed by end of July. Then interior framing phase I and zip wall install will start to be completed by end of August. Once framing is completed rough plumbing and HVAC will start.
June 26, 2019
494 7th is moving along nicely and new bulk head roof framing will start early July
May 2, 2019
494 7th Street is officially 100% fully approved by the DOB!
March 18, 2019
Final approvals coming soon!
December 16, 2018
We’ve received full approval from Landmark at 494 7th Street!