Update on 377 DeGraw
July 18, 2019
At 377 Degraw St. we are building the extension walls and demolition of rear wall is completed. Framing on the extension is now on going.
June 21, 2019
This week we will install the I-Beams for the Fire Escape, once finished the facade framing can start. HVAC and plumbing subcontractors will be back to finish their rough scope of work They are currently at 75% completion and estimated to be completed by mid-July. Upon completion the Rough Electric & Sprinklers will start.
May 13, 2019
Con Ed is bringing in new service and the new roof will go on immediately after the addition is complete.
May 2, 2019
Interior framing Phase-1 is 100% complete at 377 DeGraw Street!
March 19, 2019
The extension slab at 377 DeGraw Street has been poured and the structural steel framing is complete.
January 4, 2018
Work is progressing nicely at 377 DeGraw Street!
The concrete block installation, aka Concrete Masonry Unit (or “CMU”) installation, started on the rear extension wall. Furthermore, the interior light-gauge framing began.
December 18, 2018
Structural reinforcement of the existing joists is completed at 377 DeGraw Street!