Update on 423 3rd St
July 18, 2019
At 423 3rd St, kitchens and vanity countertops were all installed. Final MEP inspections and permit close outs are beginning in August for CO.
June 22, 2019
Kitchen cabinets and vanities were recently installed.th. Countertops were templated on the 10th, and are scheduled to be installed soon
Plumber will be starting final plumbing as soon as counter tops are installed. All appliances and final plumbing fixtures were delivered and are ready to be installed. Once installed then final paint will start and is estimated to be completed by mid-July.
May 2, 2019
We’re officially on Phase II of Finishing at 423 3rd Street!
Sheetrock taping finished mid-March and painting was started immediately thereafter.
March 19, 2019
Sheetrock is 100% complete at 423 3rd Street!
January 22, 2019
Insulation and fire stopping is 100% complete at 423 3rd Street! Sheetrock is currently underway. We expect to be 100% completed with sheetrock in the next week.
January 4, 2019
Paint and interior trim are in progress at 423 3rd Street!
December 16, 2018
Insulation and sheetrock are in progress at 423 3rd Street!