Update on 140 Luquer
July 18, 2019
Phase 2 framing at this job is has been completed. Carpenters will be finishing punch list items next week then as soon as that is completed, rough electric scope will start for 3 weeks.
July 11, 2019
We are excited to report to our equity partners that our joint investment project located at 140 Luquer Street in the Carroll Gardens section of Brooklyn, NY has been increasing in value as forecasted.
We will continue to update you through our monthly building progress reports. Should you have any questions, please do not hesitate to contact your Project Manager.
June 18, 2019
Façade framing and window opening framing is completed, and rear scaffold will be removed soon.
HVAC and plumbing subcontractors will be back to finish their rough scope of work once extension is closed and framing the interior of extension is completed.
The property will now be finishing with :
Wolf/Subzero appliance package
Custom Italian cabinetry with quartz countertops and full quartz kitchen backsplash
Engineered hardwood flooring throughout
Full height marble tile in the in master baths
Large format porcelain tile in the secondary baths
Kohler plumbing fixtures
Sierra Pacific windows
Complete façade restoration
March 19, 2019
Lots of action at 140 Luquer Street!
The Concrete Block Installation on the rear extension is complete.
January 22, 2019
The builder continues to make headway at 140 Luquer Street!
Interior Framing Phase 1 is on track to start soon.
January 4, 2019
The concrete block installation, aka Concrete Masonry Unit (or “CMU”) installation, started on the rear extension wall. Furthermore, the interior light-gauge framing began.
December 16, 2018
More information coming soon.