Update on 160 Carroll St
July 24, 2019
The 160 Carroll St. job is complete and ready for all final inspections!
Tile in the back patio was installed, garden beds are ready for some fresh plants and will be installed soon. Final electrical city inspection was scheduled for July 23rd, and the plumber is working on reserving final plumbing city inspection as well.
June 18, 2019
We have completed fence and artificial grass installation and will be completing tile installation and landscaping in the back patio by early next week. We also have final paint touch up in progress inside the building, We have also begun our final inspections of the property and are preparing for sale as soon as the NYAG report is approved.
Sell Out should happen by fall, with full returns anticipated.
May 13, 2019
160 Carroll is currently at final paint touch up that will be completed by end of this week. While that happens on the inside, we are on schedule to start lowering front yard and pouring a new finish yard on the outside.
May 3, 2019
We continue to progress nicely through the final stages of finishing at 160 Carrol Street!
Countertop installation is now completed and Final Paint is underway.
March 19, 2019
160 Carroll continues to progress nicely, and final paint should start soon!
January 22, 2019
We are in the final stages of finishing 160 Carrol Street!
December 11, 2018
The 160 Carroll St building is in its final stages of finishing and the façade restoration on the front of the building is complete. Stucco on the back of the building is being completed by the end of this week. Scaffolding will be removed tomorrow November 12. Today, kitchen cabinets were delivered. Installation will start tomorrow for all units and interior trim is in progress.