Update on 647 Warren St
July 18, 2019
647 Warren St. kitchen cabinets and vanities were installed. Countertops were templated and were recently installed. Final paint has started and estimated to be completed by mid-July.
June 19, 2019
647 Warren St. kitchen cabinets and vanities were recently installed.
Countertops were templated on the 10th, and are scheduled to be installed no later than Thursday 6/20.
Plumber will be starting final plumbing as soon as counter tops are installed.